With stage 13 titles achieved, stage 14 council inspection passed and stage 15 asphalting complete, this means we’re close to opening Murray Rd and Paynes Rd along stage 15 and 16!!

As the seasons change from the dry to wet, our delivery team must adapt on site to ensure the critical components of the construction process are progressed or protected from the seasonal conditions. For instance, mud creates difficulties for earth working and vehicular access. Flooding can affect trenches which requires pumping to clear the water before services can be laid. In spite of these difficulties, which ever construction phase your stage may be in you’ll find from our drone footage and see on the ground for yourself, your blocks continue to take shape.

With the wetter weather and cooler conditions comes autumn growth and new life breathed in to our wetlands, parks and streetscapes.

It’s nearly time for the opening of the much anticipated wetlands in stage 7 and we’d like to thank you all for your patience. Once ready to open, we will communicate to all residents and friends of Thornhill Park later this month.

Next month’s construction update will be back to the usual monthly update cycle and we look forward to sharing our progress with the community in June

Title Updates:

Stage 14 – May 2019
Phase 5: Practical Completion and Compliance

Stage 15 – July 2019
Phase 4: Roads and Streetscapes

Stage 16 – August 2019
Phase 4: Roads and Streetscapes

Stage 17 – Third Quarter 2019
Phase 4: Roads and Streetscapes

Stage 18 – Third Quarter 2019
Phase 3: Connection of Services

Stage 21 – Third Quarter 2019
Phase 3: Connection of Services

Stage 22 – Third Quarter 2019
Phase 2: Drainage

Stage 23 – Third Quarter 2019
Phase 2: Drainage

Stage 24 – Third Quarter 2019
Phase 2: Drainage

Stage 25 – Third Quarter 2019
Phase 2: Drainage

Stage 26 – Fourth Quarter 2019
Phase 1: Earthworks

Stage 27 – First Quarter 2020
Vegetation clearing to commence shortly

Stage 29 – Fourth Quarter 2019
Earthworks commencing shortly

Stage 30 – Fourth Quarter 2019
Earthworks commencing shortly

Stage 31 – First Quarter 2020

For more information on our construction process, check out our Thornhill Park Construction process blog.