We thank you for your continued patience and are pleased to advise asphalting and concreting works are well underway in stage 16, 17 & 18 with 21, 22 & 23 soon to follow suit.

Titles on stage 14 have now been registered and we’re looking forward to seeing the first homes take shape on the other side of the bridge.

Grassing and street trees will be installed throughout stages 4 and 5 this month and we thank residents in those stages in advance for their help in clearing their nature strips to assist in making this a true success.

Clear skies and hard work continue to complement our busy construction schedules as we work towards delivering your land in the fastest possible timeframe.

Title Updates:

Stage 14
Titles Achieved

Stage 15 – July 2019
Phase 4: Roads and Concrete Works

Stage 16 – August 2019
Phase 4: Roads and Concrete Works

Stage 17 – September 2019
Phase 4: Roads and Concrete Works

Stage 18 – September 2019
Phase 4: Roads and Concrete Works

Stage 21 – September 2019
Phase 4: Roads and Concrete Works

Stage 22 – October 2019
Phase 3: Connection of Services

Stage 23 – Q4 2019
Phase 2: Drainage

Stage 24 – Q4 2019
Phase 2: Drainage

Stage 25 – Q4 2019
Phase 2: Drainage

Stage 26 – Q1 2020
Phase 2: Drainage

Stage 27 – Q1 2020
Phase 1: Earthworks commencing shortly

Stage 29 – Q4 2019
Phase 1: Earthworks commencing shortly

Stage 30 – Q4 2019
Phase 1: Earthworks commencing shortly

Stage 31 – Q1 2020
Phase 1: Earthworks commencing shortly

For more information on our construction process, check out our Thornhill Park Construction process blog.

If you have any further questions, please feel free to contact:
Monique on 0488 211 250
Charmaine 0439 444 238

 

 