The beginning of this year has been challenging for our team on site across all phases of construction. Site inundation with rain and run off, extreme heat days and poor air quality have either halted construction or reduced efficiency across all construction fronts. Whilst we remain dedicated to achieving titles on Stages in the shortest possible timeframe, these unseasonal environmental influences have required us to review our programs across the estate. All of our programs now incorporate additional time required to ensure we can complete all Stages in a timeframe that respects unexpected delays that are beyond our construction team’s control.

That being said, we excitedly anticipate practical completion on four Stages in the next two months, which comprise over 230 residential lots. We are also busy finalising land areas that in the future will support; a private primary school, landscape architect designed waterways, parklands, wetlands and a local activity centre. We look forward to sharing drone footage of the estate shortly.

Here is an overview timeline (updated as per March 2020)

Stage 23 – Phase 4: Roads and Concrete Works – Expected to Title April 2020

Stage 24 – Phase 4: Roads and Concrete Works – Expected to Title April 2020

Stage 25 – Phase 4: Roads and Concrete Works – Expected to Title June 2020

Stage 26 – Phase 3: Connection of Services – Expected to Title August 2020

Stage 27 – Phase 2: Drainage – Expected to Title January 2021

Stage 29 – Phase 2: Drainage – Expected to Title February 2021

Stage 30 – Phase 1: Earthworks – Expected to Title March 2021

Stage 31 – Phase 1: Earthworks – Expected to Title April 2021

For more information on our construction process, check out our 7-phase timeline.