Construction has commenced for Stage 1 & 2 in the Mayflower Precinct at Thornhill Park.

Watch the footage above to see your new community.

Notable updates include:

  • Bulk earthworks are complete.
  • Critical path sewer network is nearly complete.
  • Drainage works are underway.
  • Water reticulation to commence 12th July – duration 2 weeks.
  • Then construction pavement layers to commence in early August.
  • Electrical road crossings in early-mid August.
  • Kerb to commence in mid-late August
  • Titles for stage 1 and 2 are anticipated for Q4 2021


We’ll continue to keep you posted as construction progresses.