October saw all projects moving ahead marvellously, what a busy month it has been. Firstly, Stage 16 titled last month which means that settlements for this stage are well underway.

More importantly, it has been a great time to celebrate as the stage has pushed Thornhill Park to titling our 1000th lot.

Thornhill Park has been steaming through production and is on schedule now that Stage 17 has titled. This will increase the total number of lots to 1,089.

Stage 18, 21 and 22 are in their final stages of compliance, with all authorities finalising their checks and balances on these stages before we can lodge for titles.

Our landscaping and fencing initiatives has been rolling out to ensure a picturesque community for our residents, designed by our residents.

Street verge frontages in Stage 6-8 are anticipated to be completed prior to summer; perfect timing for the plants and shrubs to thrive!

For those who have purchased in Stage 23 and 24, your lots are currently expected to title early 2020; new year new home.

Purchasers in Stage 24-28, the waterway adjacent to your lots have commenced works; say hello to wildlife and nature.

Below is an updated timeline overview of what is happening at Thornhill Park at this present time.

Stage 16 – October 2019
Phase 7: Settlement

Stage 17 – October 2019
Phase 6: Titles

Stage 18 – November 2019
Phase 5: Practical Completion and Compliance

Stage 21 – November 2019
Phase 5: Practical Completion and Compliance

Stage 22 – December 2019
Phase 5: Practical Completion and Compliance

Stage 23 – February 2020
Phase 4: Roads and Concrete Works

Stage 24 – January 2020
Phase 4: Roads and Concrete Works

Stage 25 – February 2020
Phase 4: Roads and Concrete Works

Stage 26 – April 2020
Phase 3: Connection of Services

Stage 27 – Q2 2020
Phase 1: Earthworks commenced

Stage 29 – Q1 2020
Phase 1: Earthworks Complete

Stage 30 – Q1 2020
Phase 1: Earthworks Underway

Stage 31 – Q2 2020
Phase 1: Earthworks Underway

For more information on our construction process, check out our 7-phase timeline.
If you have any further questions, please feel free to contact: Charmaine 0439 444 238

Back to Community