We’re excited to announce that earthworks are well underway across Stage 29 and 30, with Stage 31 earthworks commenced on site this month.

You will also notice from our drone footage that Stage 15, 16, 17 & 18 as well as Stage 21 and 22 are all nearing completion with the road network clearly defined and asphalting, footpaths, driveways, street lighting, soil preparation and line-marking works at various stages of completion across these stages.

Paynes Road Intersection will also open this month. This now totals over 3km of upgraded external roads to Thornhill Park by Welsh Developments and will allow traffic to safely access Thornhill Park on the eastern side of the estate, turning left off the Western Freeway and right on to Murray Road along the southern boundary of Stage 15, 14 and 13.

Title Updates:

Stage 15 – September 2019
Phase 5: Compliance

Stage 16 – September 2019
Phase 5: Compliance

Stage 17 – October 2019
Phase 4: Roads and Concrete Works

Stage 18 – October 2019
Phase 4: Roads and Concrete Works

Stage 21 – October 2019
Phase 4: Roads and Concrete Works

Stage 22 – October 2019
Phase 4: Roads and Concrete Works

Stage 23 – December 2019
Phase 3: Connection of Services

Stage 24 – December 2019
Phase 4: Roads and Concrete Works

Stage 25 – Q1 2020
Phase 3: Connection of Services

Stage 26 – Q1 2020
Phase 2: Drainage

Stage 27 – Q2 2020
Phase 1: Earthworks commencing next month

Stage 29 – Q1 2020
Phase 1: Earthworks underway

Stage 30 – Q1 2020
Phase 1: Earthworks Commenced

Stage 31 – Q2 2020
Phase 1: Earthworks commencing this month

 