Thornhill Park continues to take amazing strides with works on-site continuing unimpeded. Watch the footage above to see where your stage is up to.
Continue reading for a quick update on the progress at Thornhill Park or click here to visit the construction portal.
Civil Works
– Stage 26 Townhomes are due to complete in Q2
– Stage 28 Townhomes are due to complete at the end of Q1
Landscaping Works
– Stage 16 Reserve is due to commence in March 2022 with completion expected in Q2
– Stage 17 Reserve is well underway with completion expected in Q1
– RB3 wetland and drainage reserve due to commence soon with completion expected Q3
– Town Centre Park & Interface is set to commence in the coming months.
– Waterway Parcel 1 will commence in the next 2 months, completion is expected in Q3
– Stage 28 streetscapes and reserve are commencing this month.