Thornhill Park continues to take amazing strides with works on-site continuing unimpeded. Watch the footage above to see where your stage is up to.
Notable updates include:
- Stage 30A is nearing practical completion with the Statement of Compliance and titles expected in July 2021.
- Civil works Stage 28 and Stage 30B are well underway with earthworks and sewer works now complete. Drainage is also well underway.
- The Stage 17 Reserve’s turfing and planting are nearing completion.
- Hardscapes and equipment have been delayed due to COVID supply chain issues, however, we’re working with the contractor closely to ensure completion of this park occurs in Q3 2021.
- Streetscapes works are well underway for Stage 27, 29 and 30.
- Aspire Early Education and Kindergarten slab has been poured.
- Construction has commenced on Stage 1 and 2 of the Mayflower Precinct.
You can also visit the Community Portal on our website for a full breakdown on the current phases of construction at Thornhill Park.